Area Development
Capital projects come in all types and sizes. When a manufacturing company is looking to add new capacity to an existing production plant, there are many factors — and risks — that must be considered. It only takes one unplanned outage to negate much of the value of the capital improvement plan. Having a plan to address the potential issues that could impact the existing production, and using some innovative ideas to work around constraints, will result in a project that has a faster time to market without negative impacts.

{{RELATEDLINKS}} A Good Beginning
A capital project begins with identifying a need. Perhaps the need is for greater capacity, a new product, or improved reliability. Every project needs a great plan for success, and this is especially true when the project will be built in an operating plant. All of the companies I have worked with have a very well-documented, structured approach to identify projects that meet their product profile and increase or improve their production capacity, as well as identifying the equipment and capital investment needed. This is usually a collaborative effort between the manufacturer, equipment suppliers, and architect/engineer in the form of a Front-End Loading (FEL) Study. The FEL Study process is illustrated in the accompanying chart. The study phase typically incorporates stages 1, 2, and 3. At the end of Stage 3, the project is well-defined — to the point that highly accurate cost estimates and schedules can be established for construction. The main purpose of the FEL process is to establish review periods — or Stage Gates — along the way to ascertain full alignment between the project status and the original business case. As each stage is completed, the project goes through a formal review to confirm alignment with the original scope, cost, and schedule.

This article focuses on the need to plan for construction from the beginning of a project, along with the provisions that must be made throughout design and construction to be able to proceed smoothly without impacting the production of products.

It only takes one unplanned outage to negate much of the value of the capital improvement plan. First Step: Get organized! FEL-1: Planning During Concept Development Prior To Design and Major Procurement: It’s important to clearly designate where construction will occur and to identify key interface points between construction and production. FEL-2: Planning for Construction During Schematic Design FEL-3/4 (Prior to Construction Starting): Planning for Construction During Preliminary Design and Construction Documentation When the contractor mobilizes to the site, one of the first steps is to begin the segregation between areas of construction and production. FEL-5: Construction Initiation
When the contractor mobilizes to the site, one of the first steps is to begin the segregation between areas of construction and production. This includes: Containing construction hazards: Emergency egress plans may need to be altered for plant employees due to changes related to the construction project. Outage planning: To Sum Things Up
Ultimately, an effective plan for building a construction project inside an operating plant is a team sport! The plant management, production team, design team, construction team, and equipment vendors must work cooperatively to make it all work. By utilizing the best practices discussed in this article, projects will proceed with minimal interruptions to production. As one of my colleagues once said: “Production makes money; projects cost money!” And it’s of the utmost importance to keep production up and running — and still run an efficient project.